Construction Notice Angeline Rd

Please see the attached link for further information:  Notice Link


Bid Information

Fennel Creek Trail- Segment 2A
Fennel Creek Trail- Segment 2A - Bids due by 10 AM , on May 19, 2021

          *   Bid Proposal, Contract Documents and Specifications (Print Version)


          *  Bid Proposal, Contract Documents and Specifications (Screen Version)

          *   Bid Plans

          *  Addendum 1
         
          *  Addendum  2

          *  Addendum  3

          *  Bid Results             

Apparent Lowest Bidder- W.S. Contractors in the amount of $2,359,890.  Engineer’s Estimate $2,645,407.


Tacoma Point Reservoir Replacement
Tacoma Point Reservoir Replacement - Bids Due by 10 AM, May 26, 2021

          *  Bid Proposal, Contract Documents and Specifications 

          *  Bid Plans

          *  Addendum 1
     
          *  Addendum 2

          *  Addendum 3

Apparent Lowest Bidder- T. Bailey Inc in the amount of $6,210,010.66.  Engineer’s Estimate $6,385,306.00.

          *  Bid Results

          *  Bid Tabulation


                     

Elhi Hill Connection Trail
Elhi Hill Connection Trail - Bids Due by 10 AM, June 30, 2021

          * Bid Proposal, Contract Documents and Specifications (Screen)
    
          * Bid Proposal, Contract Documents and Specifications (Print)

          * Bid Plans

          * Addendum 1

          * Bid Results
Fennel Creek Trail Segment 2B-1
Fennel Creek Trail Segment 2B-1 - Bids Due by 10 AM, July 28, 2021

          * Bid Proposal, Contract Documents and Specifications

          * Bid Plans

          * Addendum 1
       
          * Bid Results
S Praire Traffic Curb Improvements
S Prairie Traffic Curb Improvements - Bids Due by 3 PM, August 5, 2021

            * Request for Quote
Fennel Creek Trail- Segment 2B-2
Fennel Creek Trail Segment 2B-2 - Bids Due by 10 AM, November 17, 2021

          *  Bid Proposal, Contract Documents and Specifications Printable

  *  Bid Proposal, Contract Documents and Specifications Screen

          *  Bid Plans

          *  Addendum 1

          *  Bid Results

         
Allan Yorke Park - Phase 1
Allan Yorke Park - Phase 1 Bids Due by 10 AM, December 1, 2021

          *  Bid Proposal, Contract Documents and Specifications Printable

          *  Bid Plans

          *  Addendum 1

The Engineer’s Estimate range is $3,900,000 - $4,300,000.



Current City Projects

Current projects are categorized below by City Managed Projects (City pays for design and construction) and Developer Managed Projects (Developer pays for design and construction).

Check the Legal Notices & Press Releases page for notices and advertisements related to these and other projects.

City Managed Projects (Capital Improvement Projects-CIP)

Bonney Lake Public Works Center Phase 3
Construction of new Public Works Center began on June 15, 2020.

Planning and design of the new Public Works Center started nearly 20 years ago as it became apparent that public works was beginning to outgrow its existing home at the former city hall building. The new facility will accommodate the expanding role of the Public Works Division in addition to housing all divisions within the larger Public Services Department – Building and Planning, Permitting, and Engineering. This will provide a much more efficient operation for Public Services as much of what the department does overlaps across each of these divisions. Locating all staff in one location instead of currently having to go to multiple facilities within the City of Bonney Lake will also make for a much more efficient experience for our residents.
Lift Station 17 Upgrade
         * Bid Advertisement March 31, 2021

         * Bid Opening April 14, 2021
Tacoma Point Reservoir Replacement
          * Finalizing Design
         
          * Out to Bid in April 2021
225th Avenue Preliminary Design

May:

  • Public Outreach Phase
    •  

     

December:

  • 30% Design Completed
SR 410 - 214th Ave Roundabout

May:

  • Public Outreach Phase
    •  

     

December:
  •  In Right Of Way Acquisition Phase

Fennel Creek Trail Segment 2A
          * In Final Design Review

          * Bid Advertisement April 2021
Fennel Creek Trail - Segment 2B-1
          * In Design
Fennel Creek Trail - Segement 2B-2
          * In Design
Elhi Hill Trail Connector
          * In Design

          * Bid Advertisement in April 2021

Developer Managed Projects

Mountain View Market Place
Chipotle Restaurant
  • Under Construction

Lot 9

  • Under Construction

 



ACD-Stobie's
Under Construction
Church Lake- was Hammond
Under Construction

Office Hours:
Monday - Friday
8:30am - 5:00pm


Contact:

City Engineer

Location:
Justice & Municipal Center
9002 Main ST E, STE 300
Bonney Lake, WA 98391

Mailing:
City of Bonney Lake
Attn: Engineering
P.O. Box 7380
Bonney Lake, WA 98391

Phone: 253-447-4356

Fax: 253-862-1116